Long Beach council to weigh $19.7M Pacific Avenue corridor construction contract
Sully-Miller Contracting would rebuild Pacific Avenue in the 1st and 6th districts under a contract with a 15 percent contingency.
Construction on the Pacific Avenue Corridor Improvements Project would be carried out by Sully-Miller Contracting Company of Brea for $17,117,131, plus a $2,567,570 contingency, for up to $19,684,701. Public Works asks the City Council to award the contract and find the work exempt from state environmental review at its November 10, 2026 meeting.
City Council vote on the contract award · Nov 10
- Long Beach City Council 18
- Long Beach Public Works Department
- Sully-Miller Contracting Company 2
- Pacific Avenue